Fresh from oven

News!!

October 10 2024

Condenser pump #1 for chiller #1 replaced by Emcor

Old Condenser pump #1
Condenser pump and motor #1 replaced (new)

October 9 2024

Compactor doors replaced by "Door People" in 900 and 910 building basement level

Compactor door 900
Compactor door 910 and 900 replaced by contractor

September 18 2024

Finished installing HVAC units for cooling rooms

Condenser unit 910
Laundry 900

September 9 2024

Carrier will start installing new HVAC units separate from the building system, as a new requirement by the City ordinance , called emergency cooling rooms. They will be installed in the 900 building laundry room and in the 910 building conference room. The work has been approved by the City of Chicago.

 July 22 2024

New chiller condenser pump and motor has been replaced by Emcor, for the chiller #2. soon we are going to replace the pump and motor for the chiller #1. It was at right time because we needed to run both chillers ( high temperatures, above 100 degree Fahrenheit)

Condenser pump and motor for chiller #2

November 2 2023

Thank you for your cooperation. Everything went well during the water shutdown. I had high hopes that it would go smoothly. The valves were replaced, and everything is back to normal. We started at 10 am, and the water was back on at 1 pm

October 31 2023

As you may have heard, we will be experiencing a water shutdown for both buildings. This will affect both hot and cold water in kitchens, laundry rooms, and bathrooms.

The water shutdown is somewhat complex but necessary to replace certain valves that require attention. While it may be inconvenient, please be aware that this shutdown has been carefully planned. Our entire team will be working diligently to ensure a smooth process, avoiding middle-of-the-night emergency shutdowns and the need to search for plumbers and materials for repairs. We ask for your patience during this time, and rest assured that the entire crew will give their all to restore water service as soon as possible.